Monday Power Update

Press Release
Working late to install overhead lines
Working late to install overhead lines
Cape Hatteras Electric Cooperative

Ocracoke is on full generator power while repairs to the cables continue.

Cape Hatteras Electric Cooperative (CHEC) continues its execution of two simultaneous solutions to restore transmission service to Hatteras and Ocracoke Islands.

Significant progress has been made on the overhead solution and today crews have already set seven of the required 10 transmission poles. Construction work will continue this evening.

Excavation and dewatering continue at the site of the damaged underground transmission cables. Two of the three cables have been uncovered. The first was severed and has already been spliced back together. Tests on the second cable indicate that it is uncompromised. Crews are close to the third cable, but because of the complex dewatering process, conditions have been challenging. PCL Construction will continue to excavate the trench through the night.

Restoring permanent transmission service as quickly and safely as possible is CHEC's top priority. The timeline for a complete repair ranges from one to two weeks. Tideland EMC members at Ocracoke Island continue to have their energy needs met by three diesel generators, and energy conservation restrictions were lifted Saturday evening at Ocracoke due to milder weather.

One line repaired already!
One line repaired already!
Tideland EMC
A view into the excavation trench as of Monday afternoon. The line being suspended by the white rope is the first excavated and repaired line.
A view into the excavation trench as of Monday afternoon. The line being suspended by the white rope is the first excavated and repaired line.
Tideland EMC
Birds-eye view of Ocracoke's electric plant.
Birds-eye view of Ocracoke's electric plant.
Tideland EMC/Rachel O'Neal

 

 

Comments powered by Disqus